top of page
- Founded in 2018 -


OFGEM Data Centre Queue: 16 September Is Not a Consultation Deadline. Its an Investment Decision.
Now that we have all returned from the summer holiday, 16 September is not far away. For most people, it is simply the closing date for an Ofgem consultation. For UK data-centre developers, investors and landowners, it may mark a more consequential shift: a grid connection can no longer be treated as a low-cost option on future capacity. Ofgem is consulting on proposals designed to remove speculative data-centre projects from the demand-connections queue. The proposal include
Aug 244 min read
The Power Illusion: Why Gas Volatility and Intermittent Grids Are Forcing Large Offtakers to SMRs
For two decades, British and European energy policy has evaluated generation economics using static Levelised Cost of Electricity (LCOE) metrics. That framework is breaking down. By measuring plant-gate generation under benign, normalized assumptions, traditional models omit the massive system integration costs of intermittent renewables and the severe tail-risk volatility of imported gas. For high-intensity energy users—hyperscale data centres, port logistics hubs, and energ
Aug 204 min read


Your Data Centre Has Become a Power Project - Whether You Planned It or Not
Data centre development was straightforward: secure land, obtain planning consent, appoint a connection adviser, procure a grid connection, and contract for power. At 20MW, that model can still work. At 200MW, 500MW or beyond, it becomes dangerously incomplete. The issue facing UK data-centre investors is not simply that grid connections take too long. It is that many projects are still being developed as real-estate schemes with a utility connection attached, when their powe
Aug 124 min read
bottom of page
